Upcoming Township Paving

Guys paving road with large truck

There are a number of upcoming paving projects occurring over the next few months. This schedule is estimated and is also weather-dependent. 


While an area is being milled, the associated work will also be completed, such as grates, catch basin repair, and topsoil, so that each road is ready to pave. Striping will be done as needed, shortly after paving is completed. The areas below are expected to be completed early to mid-December.


Paving Schedule:


Week of 9/20/21- various areas

Weeks of 9/27/21 and 10/4/21- Cherry Valley Rd

Week of 10/11/21- Lafayette Avenue, start Nelson Ridge Road

Weeks of 10/18/21 and 10/25/21- Finish Nelson Ridge Road, Start Todd Ridge Road, Keithwood Court, and Brookside Drive

Week of 11/1/21- Finish Todd Ridge, Keithwood Court, and Brookside Drive, start Lewisbrook Road

Weeks of 11/8/21 and 11/15/21- Murphy Drive, Jamieson Drive, Hessian Hill Drive, Pierson Drive, Penn View Drive, Moorehead Drive

Weeks of 11/22/21 and 11/29/21- Blue Ridge Road, Hopkinson Court