Here is the planned schedule, weather permitting, from the paving company.


Week of 7/12/2021: (Towards end of the week)

  1. Concrete:  Curb-sidewalk

Week of 7/19/2021: 

  1. All topsoil, seed, mulch at new concrete
  2. Inlet repair
  3. Start milling

Week of 7/26/21:

  1. Finish milling
  2. Base repair (where needed)
  3. Start paving 

Week of 8/2/2021:

  1. Finish paving – all striping (if we don’t finish all the week of 7/26).