Here is the planned schedule, weather permitting, from the paving company.
Week of 7/12/2021: (Towards end of the week)
- Concrete: Curb-sidewalk
Week of 7/19/2021:
- All topsoil, seed, mulch at new concrete
- Inlet repair
- Start milling
Week of 7/26/21:
- Finish milling
- Base repair (where needed)
- Start paving
Week of 8/2/2021:
- Finish paving – all striping (if we don’t finish all the week of 7/26).