Princeton Farms Sewer Rehabilitation Project Status Report February 9, 2024

Princeton Farms Sewer Rehabilitation Project Status Report

The following list identifies progress and relative action items that remain for completion of the Princeton Farms Sewer Rehabilitation Project:

Contractor completed pre-lining efforts by cleaning and televising sanitary sewer lines

Manhole frame and covers installed Contractor has completed the following lining efforts to date:

  • Darrow Drive: PF6 to MH-32 (Completed) 
  • Westcott Blvd: PF14 to PF11 (Completed)
  • Weldon Way: PF27 to PF 26 and PF30 to PF29 (Completed)
  • Pennington Rocky Hill Road: PF46 to PF43 (Completed)
  • Drummond Drive: PF41 to PF40 (Completed) 
  • Caroline Drive: MH19 to MH20 (Completed) 
  • Morris Drive: MH 8 to MH9 (Completed)

Contractor has completed all lateral lining efforts with the exception of 105  Darrow  Drive 

Contractor has completed the following manhole rehabilitation efforts:

  • Wargo Road
  • Bradford Drive

February 2024 –Grouting and Manhole Rehabilitation

Early March 2024 – Anticipated Construction Completion.


Click here to view a recording of the Zoom meeting on May 8, 2023 

Suburban Consulting Engineer presentation
Stony Brook Regional Sewer Authority presentation

Sewer Repair Flyer

Please take notice that beginning August 14, 2023, sewer repair work will begin in the Princeton Farm/Hopewell Hunt neighborhoods. Initially, sewer cleaning and video inspection will be performed. No road excavation is required, but manholes will be open during this time, requiring a partial lane closure of the road where the contractor is working.  Vehicular access is not restricted but please use caution and follow the contractor’s direction and all traffic control devices during this work.  Roads will be open to emergency vehicles, garbage trucks, mail vehicles and local traffic at all times.